Because post-frame construction differs fundamentally from traditional residential construction, understanding the engineering, site preparation requirements, and terminology is essential to making informed decisions. Below, the team at Berkey-Brewer Construction Inc (BBC) answers the most common questions brought to us by land owners, farm managers, and general contractors during initial planning consultations.

1. What is post-frame (pole building) construction, and how does it differ from traditional stick-framing?

Post-frame construction (historically referred to as "pole barn construction") is an engineered wood-frame building technique that utilizes large vertical structural posts or laminated wood columns to transfer all roof and wall loads directly into the ground or onto engineered concrete footings.

In traditional stick-frame construction (the method used in most standard suburban houses), wall studs are spaced tightly together—typically every 16 or 24 inches—and bear the weight of the roof along the entire wall length. In contrast, post-frame construction uses heavy structural columns spaced 8 to 12 feet apart.

  • Why it matters: Because post-frame structures transfer weight down concentrated post points, they do not require deep, continuous concrete foundation footings across the entire perimeter before framing begins. This significantly reduces initial excavation and concrete costs while allowing for much faster building erection without compromising structural strength.

2. What are "clear-span trusses," and why are they important for custom outbuildings?

A clear-span truss is an engineered triangular roof support system designed to span the full width of a building without requiring intermediate interior support posts or load-bearing interior walls.

  • Elementary analogy: Imagine an open airplane hangar or a covered sports stadium. The roof supports itself entirely from wall to wall, leaving the floor underneath 100% open and unobstructed.

Clear-span design is the single biggest advantage of post-frame buildings. Whether you are maneuvering large combine harvesters inside a farm shed, laying out hydraulic lifts in a custom auto restoration shop, designing stall partitions in a riding arena, or planning an open-concept floor plan for a barndominium, clear-span framing gives you total freedom to configure interior space without working around structural posts.

3. What do the terms "Girts" and "Purlins" mean in post-frame framing?

In post-frame terminology, girts and purlins are the horizontal framing members that connect the primary posts and roof trusses together:

  • Wall Girts: Heavy horizontal dimensional lumber attached across the outside or inside of the main vertical posts. They act as the ladder-like ribcage of the walls, providing structural bracing and creating the fastening surface for metal or wood exterior siding.
  • Roof Purlins: Horizontal wooden boards mounted perpendicular across the tops of the roof trusses. They tie the truss system together and serve as the mounting deck for roof panels.

By running these members horizontally across widely spaced vertical columns, post-frame structures create continuous, high-strength framework grids capable of enduring heavy Pacific Northwest wind and snow loads.

4. What site preparation is required before post-frame building construction begins?

Proper site preparation is the foundational prerequisite for a plumb, square, and long-lasting building. To ensure construction can proceed safely and on schedule, property owners are responsible for establishing a properly graded building pad prior to crew arrival.

BBC’s standard site preparation specifications require:

  1. Level Building Pad: The construction footprint must be graded level to within 1 inch of elevation across the entire building pad.
  2. Perimeter Clearance: The leveled pad must extend at least 10 feet beyond the exterior perimeter of the planned building on all sides to allow safe placement of staging equipment, scaffolding, and drilling machinery.
  3. Sub-Base Gravel: The surface should feature a minimum of 4 inches of compacted gravel base to provide adequate vehicle traction and a stable foundation for concrete slab pouring.

5. What happens if underground rock or obstruction is encountered during post-hole digging?

When digging post holes—which frequently reach depths of 4 feet or deeper depending on engineering specifications—excavation crews occasionally encounter subterranean rock ledges, heavy boulder deposits, hardpan clay, or abandoned pipe infrastructure.

In construction contracts, this contingency is managed via a standard "Rock Clause." If unmapped underground obstructions prevent standard auger drilling, work is paused, and the customer is immediately consulted. Specialized jackhammer equipment, heavy excavator attachments, or manual rock extraction necessary to achieve proper depth are billed as an additional labor/equipment project charge. Transparent site evaluation during early planning helps identify potential subterranean risks before drilling begins.

6. Can post-frame buildings be insulated and used as living spaces or commercial offices?

Yes. Post-frame construction is ideal for fully insulated, climate-controlled environments—including residential barndominiums, commercial office/warehouse facilities, and heated hobby shops.

Because posts are spaced 8 to 12 feet apart, the wall cavities in a post-frame building are far deeper and wider than the narrow 14.5-inch cavity pockets found in standard stud walls. This wide cavity spacing allows for thicker continuous insulation—such as closed-cell spray foam, commercial blanket insulation, or thick batt systems—resulting in higher thermal performance, lower energy loss, and reduced heating and cooling bills throughout Willamette Valley winters and summer heat waves.

7. How should I maintain my pole building to protect its warranty and longevity?

Berkey-Brewer Construction provides a 10-Year Workmanship Warranty covering structural integrity and roof leaks caused by installation defects, alongside manufacturer warranties covering exterior steel panels.

To protect your investment and maintain warranty coverage, routine maintenance is simple but vital:

  • Annual Exterior Cleaning: Metal siding and roof panels must be washed clean with mild detergent and low-pressure water at least once per year. Removing tree sap, moss, agricultural dust, and organic debris prevents micro-abrasions and keeps protective factory coatings intact.
  • Gutter & Ground Care: Keep roof gutters free of leaf build-up and ensure ground grading maintains slope away from post bases and concrete slabs to prevent standing water accumulation.

Start Your Custom Project with Berkey-Brewer Construction

Whether you need initial architectural advice, custom building plans, site evaluation, or a complete turn-key build, Berkey-Brewer Construction Inc brings local Pacific Northwest experience and structural expertise to every job site.

Have more questions about building codes, custom door configurations, or concrete slab options in the Willamette Valley? Contact our team today at (503) 507-4298 or submit your project details directly through our online estimate portal:


Request a Custom Quote at bbcpolebarns.com/estimate.htm

Request a Custom Quote Contact BBC
Back to Articles

Need A Pole Building Contractor? Get a Free Estimate!